DetalleParticipacionPublica

Query
Open
Range of the Standard:
Ministerial Order
Character of the query:
Policy
Type of participation:
Hearing and public information

Resumen

Proposed order establishing the values of the operation to pay for the second half of the year 2019, applicable to certain production facilities of electric power from renewable energy sources, cogeneration and residues.

The Act 24/2013, 26 December, the electricity Sector, establishes the new framework retributive of the production activity from renewable energy sources, cogeneration and residues. This new framework has been translated, first, in the Royal Decree 413/2014, 6 June, which regulates the activity of electricity production from renewable energy sources, cogeneration and residues and, secondly, through the adoption of the command IET/1045/2014, 16 June, approving restorative parameters of facilities type applicable to certain production facilities of electric power from renewable energy sources, cogeneration and residues.

The Act 24/2013, 26 December, provides in article 14.4, for the production facilities from renewable energy sources, high-efficiency cogeneration and residues with specific retributive regime, which at least annually updated pay values to the operation to those technologies whose operating costs depend essentially fuel prices.

This forecast reflects in Article 20 of the royal decree 413/2014, 6 June, which states that at least annually will be revised, according to the methodology is established regulations, pay to the operation to facilities type to the resulting from implementation and whose operating costs depend essentially fuel prices. Likewise adds that, as a result of this review, may not be suppressed or add new types of facilities to the resulting from implementation pay to the operation.

In compliance with this mandate, the command IET/1345/2015, 2 July, which establishes the methodology of updating pay to the operation of installations with specific retributive regime, regulates the methodology to update the reward for the operation of facilities with a right to the perception of specific retributive regime. this command provides that a review will be held biannually.

This command sets the values of the payment to the operation of facilities type whose operating costs depend critically on the price of fuel, which apply during the second half of natural 2019, thus acting referred to in Article 20 of the Royal Decree 413/2014, 6 June, and in Article 3 of the command IET/1345/2015, 2 July, which establishes that the update of the values of the payment to the operation will be held biannually, and apply from 1 January or since 1 July as appropriate to the first or second half of the year.

Additionally, is carried out a correction of errors on JANUARY 1ST Order/171/2020, 24 February, by which are updated restorative parameters of facilities type applicable to certain production facilities of electric power from renewable energy sources, cogeneration and residues, for the purposes of their application to regulatory period that has its start on 1 January 2020.

On 22 July 2020, posted on the website of the ministry for the ecological transition and the demographic challenge the proposal of order establishing the values of the operation to pay for the second half of the year 2019, applicable to certain production facilities of electric power from renewable energy sources, cogeneration and residues, together with his memory of regulatory impact analysis, for the purposes referred to in article 26.6 of law 50/1997, 27 December, the government.

This same text has been sent to the national commission of markets and competition to report and to by that agency is conducted trial proceedings through the Advisory Council of electricity.

Remission deadline

Deadline for submitting arguments from the day Thursday, July 23, 2020 until the day Wednesday, August 12, 2020

Submission of allegations

The allegations may be referred to the email address: bzn-sgernormativa@miteco.es

Annexes